The engineering feat at the heart of Canada’s next big Arctic build
KUGLUKTUK — Nobody lives at Grays Bay. The deepwater inlet on Nunavut's northwestern Arctic coast is ringed by treeless tundra, threaded with lakes, ponds and streams and scattered with boulders and the odd hunting cabin. There is no all-season road in. Everyt
Illustrative imageKUGLUKTUK — Nobody lives at Grays Bay.
The deepwater inlet on Nunavut's northwestern Arctic coast is ringed by treeless tundra, threaded with lakes, ponds and streams and scattered with boulders and the odd hunting cabin. There is no all-season road in. Everything needed to build one – fuel, steel, heavy equipment and people – would have to arrive by barge in the few ice-free months, or by truck over a road made of ice.
West Kitikmeot Resources Corp (WKR) plans to change that by building an all-season gravel road, a deepwater port and an airfield in a megaproject that would be a first step in connecting Nunavut by road to the rest of the country. The company says it would also provide Canada with its first deepwater seaport on the western Arctic coast, bolstering security in the North and making Grays Bay one of Canada's major economic gateways.
The goal, says Brendan Bell, WKR's CEO, is to kickstart copper and zinc mining in the area, spurring development that would ultimately funnel hundreds of millions of dollars into the economy by enabling the movement of critical minerals to international markets. "There are a number of very high-grade copper and zinc deposits that are landlocked," Bell says. "You can't fly this material out of here – you need infrastructure to get to tidewater."
Starting close to the Nunavut-Northwest Territories border and stretching 230 kilometres north along several mining deposits, Grays Bay Road and Port (GBRP) would take an estimated five years to build and cost upward of $1 billion. The project is currently before the Nunavut Impact Review Board for assessment, and Prime Minister Mark Carney has referred it to the federal major projects office, which could fast-track its construction through the federal regulatory process.
"I think Canada must do it, needs to do it," Bell says.
The more difficult question is how.
---
Ed Grozic has been down this road before. As director of Arctic engineering with Tetra Tech, he worked on the 138-kilometre Inuvik-Tuktoyaktuk Highway (ITH), which his firm helped plan, design and build before it opened in 2017.
"It's a big deal and a big challenge to complete," he says of the GBRP. It takes what he calls "alignments" – of labour, resources and equipment, but also of the people of Nunavut, governments, landowners, regulators and the environment.
Consider just the resources. The proposed road needs 15 million cubic metres of rock – enough to build the Great Pyramid of Giza six times over – and nearly all of it has to come from land it is planned to cross. In total, crews will open up to 40 new quarries along the route, blasting rock into pieces less than a metre across and crushing it into gravel. Blasting would be timed to avoid sensitive periods for wildlife, fish and migratory birds, according to WKR's filings with the review board.